Project Details:

  • Client: Dubai Aluminium (Dubal)
  • Project: Replacement of Wet Air Tank
  • Contractor: Blue Camel, Dubai
  • Application: Water Air Separator Tank

Scope of Work:

Design, Manufacturing and Testing and Commissioning of Water Air Separator Tank based on the Old Wet Air Tank installed at Plant site in 2002.

Description:

Dubai has initiated replacement of the old Wet and Dry Air System. The old machinery and Plant was installed in year 2002.

Rams International FZE, was selected to Design, Manufacture and supply the Water air Separator Tank as per data available at the project site.

Manufacturing of Water Air Separator Tank was done in our factory and was supplied to our customer. Several Parts were specially manufactured for this project by different vendors in India and were assembled at our factory. The discussions and consultation was taken while work was on.